2024欧洲杯下注平台 > Project construction

  On the morning of March 14, the first steel anchor beam and the general acceptance meeting of G3 Tongling Yangtze River Railway Bridge South Tower was successfully held in Yixing, Jiangsu Province。Group company party committee member, deputy general manager, Tongling Yangtze River Railway Bridge Investment Co., LTD. General manager Tang Shicai attended the acceptance meeting。

  Tang Shicai first went to the acceptance site, detailed understanding of the first steel anchor beam manufacturing, assembly process, structural characteristics and important and difficult analysis of the content, and went to the construction workshop to view the production progress of the main beam。

  Subsequently, an acceptance meeting was organized。The inspection group carefully listened to the production unit's summary report on the manufacturing technology of steel anchor beam head parts, and inquired the relevant information。After sufficient inquiry and discussion, the acceptance group agreed that the first piece and the general assembly of steel anchor beam were complete, the test results met the "G3 Tongling Yangtze River Bridge Steel structure manufacturing Rules" and design requirements, and could be mass-produced。

  It is reported that there are 56 sets of steel anchor beams in the whole bridge, each set of steel anchor beams anchoring a pair of cable-stayed cables, of which 28 sets of steel anchor beams in the south tower are used for the construction of the No. 4 main pier。The acceptance of the first piece and the total piece of the steel anchor beam marked that the manufacturing of the steel anchor beam of the G3 railway bridge officially entered the mass production stage, which laid a solid foundation for the next construction of the No. 4 main tower and provided a favorable guarantee for creating "G3 speed"。

  G3 Railway bridge project office, design, construction, supervision, third-party testing and manufacturing units related personnel attended the meeting。